Phase 1 Timeline

Below is a possible timeline for the phase one expansion.


Spring 2008 Preparation of Design Documents for parking lot and related site work.

Summer 2008 Submittal/Approval/Advertisement for bids/Award construction contract.

October 2008 Official Groundbreaking for Expansion.
Base paving on HSCC property.

Nov 08 - Mar 09 Site construction to point where site is usable and ready for building foundations.

March 2009 Building pad finished, Construction begins in earnest.

Fall 2010 Expansion building project completed.

Note: If HSCC vacates by end of June 2010, if money is available, renovation of HSCC and completed LHBC expansion could coincide.